Action Date | Action Description |
---|---|
Mar 31, 2021 | Assent Application Received |
Apr 06, 2021 | Administrative Review for Completeness |
Apr 06, 2021 | CHA Worksheet received |
Apr 21, 2021 | Additional Information Requested from Applicant |
Apr 27, 2021 | Correspondence Received |
May 07, 2021 | Application Accepted |
May 07, 2021 | Bio Team Review for Completeness |
Jun 10, 2021 | HPHC Review Pending |
Jun 10, 2021 | HPHC Historical Preservation No Effect |
Jun 18, 2021 | Additional Information Received |
Aug 06, 2021 | Additional Information Requested from Applicant |
Aug 06, 2021 | Additional Information Requested from Applicant |
May 19, 2022 | Additional Information Received |
Aug 05, 2022 | Ready to Schedule Semi-Monthly Meeting |
Aug 05, 2022 | Mail Agenda Notice |
Aug 15, 2022 | Additional Information Received |
Aug 16, 2022 | Additional Information Received |
Aug 16, 2022 | Biologist Report |
Aug 16, 2022 | Executive Signoff of Staff Reports |
Aug 17, 2022 | Supervisor Biologist SignOff |
Aug 17, 2022 | Supervisor Engineer SignOff |
Aug 23, 2022 | Semi-Monthly Meeting Date Scheduled |
Aug 23, 2022 | Council Approval Granted |
Oct 11, 2022 | Legal Response/Decision |
Oct 13, 2022 | 30 Day Appeal Notification to Owner |
Oct 14, 2022 | Stipulation Package from Biologist |
Oct 19, 2022 | Permit Mailed |
Oct 19, 2022 | Typist for Processing |
Oct 19, 2022 | Executive Sign Off |
Oct 19, 2022 | Sent to Photo Copy |
Oct 19, 2022 | Permit Approved |
Oct 26, 2022 | Commencement of Work Notice received |
Oct 27, 2022 | Land Evidence Date |
Jul 21, 2023 | Assent Requirement |