Action Date | Action Description |
---|---|
Apr 05, 2021 | Assent Application Received |
Apr 12, 2021 | Administrative Review for Completeness |
Apr 16, 2021 | Bio Team Review for Completeness |
Apr 16, 2021 | Application Accepted |
Apr 17, 2021 | Project Manager |
Apr 17, 2021 | Category A* (Docks) |
May 06, 2021 | 30 day Public Notice Issued |
Jun 06, 2021 | Public Notice End Date |
Jun 17, 2021 | Dock Meeting -- Approval |
Jul 07, 2021 | HPHC Historical Preservation No Effect |
Jul 07, 2021 | HPHC Review Pending |
Jul 13, 2021 | Biologist Report |
Jul 13, 2021 | Stipulation Package from Biologist |
Jul 19, 2021 | Typist for Processing |
Jul 19, 2021 | Executive Sign Off |
Jul 19, 2021 | Sent to Photo Copy |
Jul 19, 2021 | Permit Approved |
Jul 22, 2021 | Permit Mailed |
Jul 28, 2021 | Land Evidence Date |
Mar 01, 2023 | Dock Post-Construction Certification by Engineer received. |