Action Date | Action Description |
---|---|
Apr 14, 2021 | Assent Application Received |
Apr 19, 2021 | Administrative Review for Completeness |
Apr 22, 2021 | Bio Team Review for Completeness |
Apr 22, 2021 | Application Accepted |
Apr 23, 2021 | Project Manager |
May 03, 2021 | HPHC Historical Preservation Comments/Concerns |
May 03, 2021 | HPHC Review Pending |
May 17, 2021 | HPHC Historical Preservation No Effect |
May 18, 2021 | Stipulation Package from Biologist |
May 18, 2021 | Biologist Report |
May 21, 2021 | Typist for Processing |
May 25, 2021 | Executive Sign Off |
May 25, 2021 | Sent to Photo Copy |
May 25, 2021 | Permit Approved |
Jun 01, 2021 | Land Evidence Date |