Action Date | Action Description |
---|---|
Apr 27, 2021 | Assent Application Received |
May 03, 2021 | Administrative Review for Completeness |
May 27, 2021 | Bio Team Review for Completeness |
May 27, 2021 | Application Accepted |
May 28, 2021 | Project Manager |
Jun 02, 2021 | Additional Information Received |
Jun 02, 2021 | CHA Worksheet received |
Jun 14, 2021 | HPHC Historical Preservation No Effect |
Jun 14, 2021 | HPHC Review Pending |
Dec 06, 2021 | Plans Received |
Jan 20, 2022 | Additional Information Received |
Mar 25, 2022 | Additional Information Received |
May 02, 2022 | Additional Information Received |
May 26, 2022 | Biologist Report |
Jun 01, 2022 | Permit Mailed |
Jun 01, 2022 | Typist for Processing |
Jun 01, 2022 | Executive Sign Off |
Jun 01, 2022 | Sent to Photo Copy |
Jun 01, 2022 | Permit Approved |
Jun 03, 2022 | Permit Mailed |
Jun 06, 2022 | Land Evidence Date |