Action Date | Action Description |
---|---|
May 13, 2021 | Maintenance Certification Request |
May 17, 2021 | Administrative Review for Completeness |
May 18, 2021 | Additional Information Requested from Applicant |
May 18, 2021 | Additional Information Received |
May 18, 2021 | Additional Information Requested from Applicant |
May 19, 2021 | CHA Worksheet received |
May 26, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 27, 2021 | Additional Information Received |
May 28, 2021 | Assent Application Received |
Jun 01, 2021 | Application Accepted |
Jun 01, 2021 | Bio Team Review for Completeness |
Jun 02, 2021 | Project Manager |
Jun 14, 2021 | Note to File |
Jun 14, 2021 | HPHC Historical Preservation No Effect |
Jun 14, 2021 | HPHC Review Pending |
Jun 23, 2021 | Correspondence Received |
Jun 23, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 01, 2021 | Correspondence Received |
Jul 15, 2021 | Additional Information Received |
Jul 19, 2021 | Additional Information Requested from Applicant |
Jul 30, 2021 | Plans Received |
Aug 16, 2021 | Stipulation Package from Biologist |
Aug 16, 2021 | Biologist Report |
Aug 20, 2021 | Typist for Processing |
Aug 20, 2021 | Executive Sign Off |
Aug 20, 2021 | Sent to Photo Copy |
Aug 20, 2021 | Permit Approved |
Aug 24, 2021 | Permit Mailed |
Aug 31, 2021 | Land Evidence Date |