Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
May 24, 2021 | Assent Application Received |
May 25, 2021 | Administrative Review for Completeness |
May 27, 2021 | Bio Team Review for Completeness |
May 27, 2021 | Category B assigned |
May 28, 2021 | Application Accepted |
May 28, 2021 | Project Manager |
May 28, 2021 | Eng Team Review for Completeness |
Jun 10, 2021 | HPHC Review Pending |
Jun 10, 2021 | HPHC Historical Preservation No Effect |
Jul 07, 2021 | Additional Information Received |
Jul 16, 2021 | 30 day Public Notice Issued |
Jul 27, 2021 | Additional Information Received |
Aug 16, 2021 | Public Notice End Date |
Aug 20, 2021 | Dock Meeting -- Approval |
Nov 05, 2021 | Plans Received |
Dec 02, 2021 | Stipulation Package by Engineer |
Dec 02, 2021 | Engineering Report |
Dec 03, 2021 | Typist for Processing |
Dec 03, 2021 | Executive Sign Off |
Dec 03, 2021 | Sent to Photo Copy |
Dec 03, 2021 | Permit Approved |
Dec 07, 2021 | Permit Mailed |
Dec 13, 2021 | Land Evidence Date |