Action Date | Action Description |
---|---|
Jun 14, 2021 | Assent Application Received |
Jun 18, 2021 | Administrative Review for Completeness |
Jun 21, 2021 | Bio Team Review for Completeness |
Jun 30, 2021 | Correspondence Received |
Jul 01, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 20, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 20, 2021 | Correspondence Received |
Jul 23, 2021 | Application Accepted |
Jul 23, 2021 | Project Manager |
Jul 23, 2021 | Bio Team Review for Completeness |
Aug 20, 2021 | HPHC Review Pending |
Aug 20, 2021 | HPHC Historical Preservation No Effect |
Sep 01, 2021 | Biologist Report |
Sep 02, 2021 | Stipulation Package from Biologist |
Sep 07, 2021 | Typist for Processing |
Sep 07, 2021 | Executive Sign Off |
Sep 07, 2021 | Sent to Photo Copy |
Sep 07, 2021 | Permit Approved |
Sep 07, 2021 | Permit Mailed |
Sep 24, 2021 | Assent Correction Request Received |
Sep 27, 2021 | Assent Correction Mailed |
Oct 01, 2021 | Land Evidence Date |