Action Date | Action Description |
---|---|
HPHC Review Pending | |
Jun 16, 2021 | Assent Application Received |
Jun 22, 2021 | Administrative Review for Completeness |
Jun 22, 2021 | CHA Worksheet received |
Jun 25, 2021 | Bio Team Review for Completeness |
Jun 25, 2021 | Application Accepted |
Jun 28, 2021 | Project Manager |
Jul 21, 2021 | HPHC Historical Preservation No Effect |
Jul 21, 2021 | HPHC Review Pending |
Aug 26, 2021 | Stipulation Package from Biologist |
Aug 26, 2021 | Biologist Report |
Aug 27, 2021 | Typist for Processing |
Aug 27, 2021 | Executive Sign Off |
Aug 27, 2021 | Sent to Photo Copy |
Aug 27, 2021 | Permit Approved |
Aug 31, 2021 | Permit Mailed |
Sep 15, 2021 | Duplicate Original Assent requested/mailed |
Nov 04, 2021 | Modification Request |
Nov 05, 2021 | Administrative Review for Completeness |
Nov 08, 2021 | Additional Information Received |
Dec 07, 2021 | Additional Information Received |
Dec 10, 2021 | Additional Information Received |
Dec 10, 2021 | Bio Team Review for Completeness |
Dec 17, 2021 | Typist for Processing |
Dec 17, 2021 | Executive Sign Off |
Dec 17, 2021 | Sent to Photo Copy |
Dec 21, 2021 | Permit Mailed |
Dec 21, 2021 | Modification Approved |
Dec 21, 2021 | Land Evidence Date |