Action Date | Action Description |
---|---|
Jun 23, 2021 | Assent Application Received |
Jun 23, 2021 | Administrative Review for Completeness |
Jun 25, 2021 | Eng Team Review for Completeness |
Jun 25, 2021 | Application Accepted |
Jun 28, 2021 | Project Manager |
Jun 28, 2021 | Engineering Report |
Jun 28, 2021 | Stipulation Package by Engineer |
Jun 30, 2021 | Typist for Processing |
Jun 30, 2021 | Permit Approved |
Jul 01, 2021 | HPHC Historical Preservation No Effect |
Jul 01, 2021 | HPHC Review Pending |