Action Date | Action Description |
---|---|
Jun 25, 2021 | Buffer Zone Management Application Received |
Jun 30, 2021 | Administrative Review for Completeness |
Jul 28, 2021 | Bio Team Review for Completeness |
Jul 28, 2021 | Deficient Application - Owner Notification Sent |
Aug 16, 2021 | Deficient Application Picked Up |
Nov 26, 2021 | Deficiency Response Received |
Dec 03, 2021 | Bio Team Review for Completeness |
Dec 03, 2021 | Application Accepted |
Dec 06, 2021 | Project Manager |
Dec 15, 2021 | HPHC Historical Preservation No Effect |
Dec 15, 2021 | HPHC Review Pending |
May 12, 2022 | Additional Information Received |
May 13, 2022 | Biologist Report |
May 16, 2022 | Permit Mailed |
May 16, 2022 | Typist for Processing |
May 16, 2022 | Permit Approved |
May 19, 2022 | Land Evidence Date |