Action Date | Action Description |
---|---|
HPHC Historical Preservation No Effect | |
Jun 28, 2021 | Maintenance Certification Request |
Jul 01, 2021 | Administrative Review for Completeness |
Jul 13, 2021 | Eng Team Review for Completeness |
Jul 13, 2021 | Application Accepted |
Jul 13, 2021 | Project Manager |
Jul 13, 2021 | Engineering Report |
Jul 14, 2021 | Stipulation Package by Engineer |
Aug 04, 2021 | HPHC Review Pending |
Aug 06, 2021 | Typist for Processing |
Aug 06, 2021 | Executive Sign Off |
Aug 06, 2021 | Sent to Photo Copy |
Aug 06, 2021 | Permit Approved |
Aug 12, 2021 | Permit Mailed |
Aug 19, 2021 | Land Evidence Date |