Action Date | Action Description |
---|---|
Jun 29, 2021 | Assent Application Received |
Jul 02, 2021 | Administrative Review for Completeness |
Jul 15, 2021 | Bio Team Review for Completeness |
Jul 15, 2021 | Application Accepted |
Jul 15, 2021 | Project Manager |
Jul 16, 2021 | Additional Information Requested from Applicant |
Jul 19, 2021 | Additional Information Received |
Jul 21, 2021 | HPHC Review Pending |
Jul 21, 2021 | HPHC Historical Preservation No Effect |
Jul 23, 2021 | Note to File |
Aug 10, 2021 | Correspondence Received |
Sep 07, 2021 | Stipulation Package from Biologist |
Sep 07, 2021 | Biologist Report |
Sep 10, 2021 | Typist for Processing |
Sep 10, 2021 | Executive Sign Off |
Sep 10, 2021 | Sent to Photo Copy |
Sep 10, 2021 | Permit Approved |
Sep 13, 2021 | Permit Mailed |
Oct 19, 2021 | Duplicate Original Assent requested/mailed |
Nov 29, 2021 | Land Evidence Date |