Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jul 07, 2021 | Assent Application Received |
Jul 09, 2021 | Administrative Review for Completeness |
Jul 09, 2021 | Category A* (Docks) |
Jul 27, 2021 | Application Accepted |
Jul 27, 2021 | Bio Team Review for Completeness |
Jul 28, 2021 | Project Manager |
Aug 05, 2021 | HPHC Historical Preservation No Effect |
Aug 05, 2021 | HPHC Review Pending |
Sep 08, 2021 | 30 day Public Notice Issued |
Oct 08, 2021 | Public Notice End Date |
Oct 14, 2021 | Dock Meeting -- Approval |
Oct 15, 2021 | Stipulation Package from Biologist |
Oct 15, 2021 | Biologist Report |
Oct 20, 2021 | Typist for Processing |
Oct 20, 2021 | Executive Sign Off |
Oct 20, 2021 | Sent to Photo Copy |
Oct 20, 2021 | Permit Approved |
Oct 22, 2021 | Permit Mailed |
Nov 18, 2021 | US Army Corps of Engineers Approval Received |
Nov 19, 2021 | Land Evidence Date |