Action Date | Action Description |
---|---|
Jul 15, 2021 | Buffer Zone Management Application Received |
Jul 16, 2021 | Administrative Review for Completeness |
Jul 23, 2021 | Bio Team Review for Completeness |
Jul 23, 2021 | Application Accepted |
Jul 23, 2021 | Project Manager |
Aug 20, 2021 | HPHC Review Pending |
Aug 20, 2021 | HPHC Historical Preservation No Effect |
Sep 10, 2021 | Additional Information Received |
Oct 25, 2021 | Correspondence Received |
Oct 28, 2021 | Correspondence Mailed/Faxed/E-mailed |
Dec 15, 2021 | Note to File |
Dec 16, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jan 05, 2022 | Additional Information Received |
Feb 16, 2022 | Note to File |
Mar 02, 2022 | Note to File |
Mar 02, 2022 | Additional Information Requested from Applicant |
Mar 31, 2022 | Additional Information Received |
May 19, 2022 | Biologist Report |
May 24, 2022 | Permit Mailed |
May 24, 2022 | Typist for Processing |
May 24, 2022 | Executive Sign Off |
May 24, 2022 | Sent to Photo Copy |
May 24, 2022 | Permit Approved |
May 27, 2022 | Permit Mailed |
Jun 06, 2022 | Land Evidence Date |