Action Date | Action Description |
---|---|
Monitoring Report | |
Jul 27, 2021 | Assent Application Received |
Jul 29, 2021 | Administrative Review for Completeness |
Aug 11, 2021 | Note to File |
Aug 11, 2021 | Application Accepted |
Aug 12, 2021 | Project Manager |
Aug 20, 2021 | HPHC Review Pending |
Aug 20, 2021 | HPHC Historical Preservation No Effect |
Oct 08, 2021 | Stipulation Package from Biologist |
Oct 08, 2021 | Typist for Processing |
Oct 08, 2021 | Executive Sign Off |
Oct 08, 2021 | Sent to Photo Copy |
Oct 08, 2021 | Permit Approved |
Oct 08, 2021 | Biologist Report |
Oct 08, 2021 | Policy Review |
Oct 14, 2021 | Permit Mailed |
Oct 28, 2021 | Note to File |
Nov 02, 2021 | Land Evidence Date |
Dec 15, 2023 | Monitoring Report |
Aug 19, 2024 | Extension of Permit Request |
Aug 20, 2024 | Extension Approved |