Action Date | Action Description |
---|---|
Aug 02, 2021 | Assent Application Received |
Aug 06, 2021 | Administrative Review for Completeness |
Aug 06, 2021 | CHA Worksheet received |
Aug 18, 2021 | Bio Team Review for Completeness |
Aug 18, 2021 | Application Accepted |
Aug 19, 2021 | Project Manager |
Sep 16, 2021 | HPHC Review Pending |
Sep 16, 2021 | HPHC Historical Preservation No Effect |
Nov 16, 2021 | Plans Received |
Nov 18, 2021 | Plans Received |
Dec 06, 2021 | Additional Information Received |
Dec 21, 2021 | Objections/Comments Received |
Jan 10, 2022 | Comments Received |
Jan 11, 2022 | Letter of Support for Project |
Jan 12, 2022 | Additional Information Received |
May 24, 2022 | Letter of Support for Project |
May 25, 2022 | Letter of Support for Project |
May 27, 2022 | Letter of Support for Project |
Aug 05, 2022 | Ready to Schedule Semi-Monthly Meeting |
Aug 05, 2022 | Mail Agenda Notice |
Aug 18, 2022 | Biologist Report |
Aug 23, 2022 | Council Approval Granted |
Aug 23, 2022 | Semi-Monthly Meeting Date Scheduled |
Aug 29, 2022 | Plans Received |
Aug 30, 2022 | Plans Received |
Sep 28, 2022 | 30 Day Appeal Notification to Owner |
Sep 28, 2022 | Legal Response/Decision |
Oct 04, 2022 | Stipulation Package from Biologist |
Oct 05, 2022 | Permit Mailed |
Oct 05, 2022 | Typist for Processing |
Oct 05, 2022 | Executive Sign Off |
Oct 05, 2022 | Sent to Photo Copy |
Oct 05, 2022 | Permit Approved |
Oct 11, 2022 | Permit Mailed |
Oct 24, 2022 | Land Evidence Date |