Aug 16, 2021 | Assent Application Received |
Aug 17, 2021 | Administrative Review for Completeness |
Aug 17, 2021 | CHA Worksheet received |
Aug 19, 2021 | Additional Information Requested from Applicant |
Sep 02, 2021 | Additional Information Requested from Applicant |
Sep 02, 2021 | Additional Information Received |
Sep 10, 2021 | Application Accepted |
Sep 10, 2021 | Project Manager |
Sep 10, 2021 | Bio Team Review for Completeness |
Oct 26, 2021 | HPHC Review Pending |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Oct 28, 2021 | Biologist Report |
Nov 03, 2021 | Typist for Processing |
Nov 03, 2021 | Executive Sign Off |
Nov 03, 2021 | Sent to Photo Copy |
Nov 03, 2021 | Permit Approved |
Nov 08, 2021 | Permit Mailed |
Aug 08, 2022 | Land Evidence Date |