Action Date | Action Description |
---|---|
Aug 18, 2021 | Assent Application Received |
Aug 19, 2021 | Administrative Review for Completeness |
Aug 19, 2021 | CHA Worksheet received |
Aug 25, 2021 | Bio Team Review for Completeness |
Aug 25, 2021 | Application Accepted |
Aug 25, 2021 | Project Manager |
Sep 15, 2021 | HPHC Historical Preservation No Effect |
Sep 15, 2021 | HPHC Review Pending |
Sep 27, 2021 | Additional Information Requested from Applicant |
Sep 28, 2021 | Additional Information Received |
Oct 04, 2021 | Note to File |
Oct 04, 2021 | Additional Information Requested from Applicant |
Jan 12, 2022 | Note to File |
Jan 18, 2022 | Additional Information Requested from Applicant |
Jan 31, 2022 | Plans Received |
Jan 31, 2022 | Biologist Report |
Feb 02, 2022 | Typist for Processing |
Feb 02, 2022 | Executive Sign Off |
Feb 02, 2022 | Sent to Photo Copy |
Feb 02, 2022 | Permit Approved |
Feb 04, 2022 | Permit Mailed |
Jan 12, 2023 | Land Evidence Date |
Jun 10, 2024 | Modification Request |
Jun 17, 2024 | Administrative Review for Completeness |
Jun 18, 2024 | Additional Information Received |
Jun 21, 2024 | Bio Team Review for Completeness |
Jun 21, 2024 | Project Manager |
Jun 27, 2024 | HPHC Historical Preservation No Effect |
Jul 12, 2024 | Biologist Report |
Aug 14, 2024 | Typist for Processing |
Aug 16, 2024 | Executive Sign Off |
Aug 16, 2024 | Sent to Photo Copy |
Aug 19, 2024 | Permit Mailed |
Sep 13, 2024 | Additional Information Received |
Sep 17, 2024 | Modification Approved |
Sep 17, 2024 | Modification mailed |