Action Date | Action Description |
---|---|
Aug 18, 2021 | Assent Application Received |
Aug 19, 2021 | Administrative Review for Completeness |
Aug 20, 2021 | Bio Team Review for Completeness |
Aug 20, 2021 | Application Accepted |
Aug 24, 2021 | Project Manager |
Aug 31, 2021 | Additional Information Received |
Sep 16, 2021 | HPHC Historical Preservation No Effect |
Sep 17, 2021 | Stipulation Package from Biologist |
Sep 17, 2021 | Biologist Report |
Sep 21, 2021 | Typist for Processing |
Sep 21, 2021 | Executive Sign Off |
Sep 21, 2021 | Sent to Photo Copy |
Sep 21, 2021 | Permit Approved |
Sep 22, 2021 | Permit Mailed |
Sep 28, 2021 | Land Evidence Date |