Action Date | Action Description |
---|---|
Aug 25, 2021 | Assent Application Received |
Aug 31, 2021 | Administrative Review for Completeness |
Aug 31, 2021 | CHA Worksheet received |
Sep 03, 2021 | Bio Team Review for Completeness |
Sep 03, 2021 | Application Accepted |
Sep 03, 2021 | Project Manager |
Oct 26, 2021 | HPHC Review Pending |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Nov 15, 2021 | Additional Information Requested from Applicant |
Dec 13, 2021 | Plans Received |
Dec 30, 2021 | Plans Received |
Jan 10, 2022 | Plans Received |
Jan 11, 2022 | Biologist Report |
Jan 12, 2022 | Typist for Processing |
Jan 12, 2022 | Permit Approved |
Jan 18, 2022 | Permit Mailed |
Jan 25, 2022 | Land Evidence Date |
Sep 27, 2022 | Note to File |
Oct 06, 2022 | Assent Requirement |