Image not found

Application 2021-08-107 Details

Back to List


Actions:

Action Date Action Description
Legal Response/Decision
Under Review/Decision
Aug 25, 2021 Assent Application Received
Aug 31, 2021 Administrative Review for Completeness
Sep 01, 2021 Eng Team Review for Completeness
Sep 01, 2021 Bio Team Review for Completeness
Sep 01, 2021 Application Accepted
Sep 01, 2021 Project Manager
Oct 01, 2021 HPHC Review Pending
Oct 01, 2021 HPHC Historical Preservation No Effect
Oct 21, 2021 30 day Public Notice Issued
Nov 21, 2021 Public Notice End Date
Feb 18, 2022 Public Hearing Notices Mailed
Mar 01, 2022 Biologist Report
Mar 01, 2022 Engineering Report
Mar 01, 2022 Additional Information Received
Mar 22, 2022 Council Approval Granted
Mar 22, 2022 Semi-Monthly Meeting Date Scheduled
Mar 24, 2022 Stipulation Package by Engineer
Mar 29, 2022 Permit Approved
Mar 29, 2022 Typist for Processing
Mar 29, 2022 Executive Sign Off
Mar 29, 2022 Sent to Photo Copy
Mar 30, 2022 Permit Mailed
Apr 07, 2022 Land Evidence Date
Nov 17, 2023 Modification Request
Nov 21, 2023 Administrative Review for Completeness
Dec 14, 2023 Bio Team Review for Completeness
Dec 14, 2023 Modification Approved

Details:

File No
2021-08-107
Town
New Shoreham
First Name
Town of New Shoreham
Last Name
Street
Champlin Road
Location
121 Champlin Road
Plat/Map
20
Lot/Block
12
Decision Date
Mar 29, 2022
Dock Reg.No
Project
Reconfigure existing Coast Guard Dock, widening pier and adding a fixed timber pier.
Description
Docks, Piers, Floats (Non-Residential)
Water Area
Easement
0
Acceptance Date
Sep 01, 2021

Back to List