Action Date | Action Description |
---|---|
Sep 02, 2021 | Assent Application Received |
Sep 08, 2021 | Administrative Review for Completeness |
Sep 09, 2021 | Bio Team Review for Completeness |
Sep 09, 2021 | Application Accepted |
Sep 09, 2021 | Project Manager |
Sep 24, 2021 | CHA Worksheet received |
Sep 28, 2021 | Biologist Report |
Oct 05, 2021 | HPHC Review Pending |
Oct 05, 2021 | HPHC Historical Preservation No Effect |
Oct 06, 2021 | Additional Information Received |
Jan 14, 2022 | Mail Agenda Notice |
Jan 25, 2022 | Council Approval Granted |
Jan 25, 2022 | Semi-Monthly Meeting Date Scheduled |
Feb 10, 2022 | Stipulation Package from Biologist |
Feb 18, 2022 | Typist for Processing |
Feb 18, 2022 | Executive Sign Off |
Feb 18, 2022 | Sent to Photo Copy |
Feb 18, 2022 | Permit Approved |
Feb 23, 2022 | Permit Mailed |
Mar 04, 2022 | Land Evidence Date |
Mar 10, 2022 | 30 Day Appeal Notification to Owner |
Mar 10, 2022 | Legal Response/Decision |