Action Date | Action Description |
---|---|
Sep 03, 2021 | Assent Application Received |
Sep 09, 2021 | Administrative Review for Completeness |
Sep 09, 2021 | CHA Worksheet received |
Sep 15, 2021 | Bio Team Review for Completeness |
Sep 15, 2021 | Project Manager |
Sep 15, 2021 | Application Accepted |
Sep 16, 2021 | Plans Received |
Sep 16, 2021 | Additional Information Received |
Sep 21, 2021 | Additional Information Requested from Applicant |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Nov 18, 2021 | Additional Information Received |
Nov 22, 2021 | Biologist Report |
Jan 21, 2022 | Typist for Processing |
Jan 21, 2022 | Executive Sign Off |
Jan 21, 2022 | Sent to Photo Copy |
Jan 21, 2022 | Permit Approved |
Jan 24, 2022 | Permit Mailed |
Feb 16, 2022 | Land Evidence Date |