Action Date | Action Description |
---|---|
Sep 10, 2021 | Assent Application Received |
Sep 16, 2021 | Administrative Review for Completeness |
Sep 16, 2021 | CHA Worksheet received |
Sep 17, 2021 | Bio Team Review for Completeness |
Sep 17, 2021 | Application Accepted |
Sep 20, 2021 | Project Manager |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Oct 26, 2021 | HPHC Review Pending |
Nov 12, 2021 | Biologist Report |
Nov 16, 2021 | Typist for Processing |
Nov 16, 2021 | Executive Sign Off |
Nov 16, 2021 | Sent to Photo Copy |
Nov 16, 2021 | Permit Approved |
Nov 18, 2021 | Permit Mailed |
Dec 17, 2021 | Land Evidence Date |
Dec 21, 2021 | Note to File |