Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 15, 2021 | Assent Application Received |
Sep 20, 2021 | Administrative Review for Completeness |
Nov 04, 2021 | Bio Team Review for Completeness |
Nov 04, 2021 | Application Accepted |
Nov 05, 2021 | Project Manager |
Nov 05, 2021 | Category A* (Docks) |
Nov 17, 2021 | HPHC Review Pending |
Nov 17, 2021 | HPHC Historical Preservation No Effect |
Dec 03, 2021 | US Army Corps of Engineers Approval Received |
Dec 06, 2021 | 30 day Public Notice Issued |
Jan 06, 2022 | Public Notice End Date |
Mar 03, 2022 | Additional Information Received |
Apr 04, 2022 | Engineering Report |
Apr 04, 2022 | Mail Agenda Notice |
Apr 06, 2022 | Supervisor Biologist SignOff |
Apr 06, 2022 | Supervisor Engineer SignOff |
Apr 07, 2022 | Executive Signoff of Staff Reports |
Apr 12, 2022 | Council Approval Granted |
Apr 12, 2022 | Semi-Monthly Meeting Date Scheduled |
Nov 02, 2022 | Stipulation Package by Engineer |
Nov 09, 2022 | Legal Response/Decision |
Nov 09, 2022 | 30 Day Appeal Notification to Owner |
Jan 17, 2023 | Permit Approved |
Jan 19, 2023 | Permit Mailed |
Oct 20, 2023 | Land Evidence Date |