Action Date | Action Description |
---|---|
Sep 17, 2021 | Assent Application Received |
Sep 21, 2021 | Administrative Review for Completeness |
Sep 23, 2021 | Bio Team Review for Completeness |
Sep 23, 2021 | Application Accepted |
Sep 23, 2021 | Project Manager |
Sep 27, 2021 | Additional Information Requested from Applicant |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Oct 26, 2021 | Additional Information Received |
Dec 14, 2021 | Biologist Report |
Jan 21, 2022 | Typist for Processing |
Jan 21, 2022 | Executive Sign Off |
Jan 21, 2022 | Sent to Photo Copy |
Jan 25, 2022 | Permit Approved |
Jan 27, 2022 | Permit Mailed |
Feb 02, 2022 | Land Evidence Date |