Action Date | Action Description |
---|---|
Sep 29, 2021 | Assent Application Received |
Oct 05, 2021 | Administrative Review for Completeness |
Oct 05, 2021 | CHA Worksheet received |
Oct 06, 2021 | Bio Team Review for Completeness |
Oct 06, 2021 | Application Accepted |
Oct 07, 2021 | Project Manager |
Nov 05, 2021 | HPHC Review Pending |
Nov 05, 2021 | HPHC Historical Preservation No Effect |
Nov 08, 2021 | Biologist Report |
Nov 09, 2021 | Typist for Processing |
Nov 09, 2021 | Executive Sign Off |
Nov 09, 2021 | Sent to Photo Copy |
Nov 09, 2021 | Permit Approved |
Nov 16, 2021 | Permit Mailed |
Nov 23, 2021 | Land Evidence Date |
Aug 31, 2023 | Correspondence Mailed/Faxed/E-mailed |
Sep 07, 2023 | Phone Call |
Sep 08, 2023 | Correspondence Received |
Sep 08, 2023 | Assent Requirement |