Action Date | Action Description |
---|---|
Assent Requirement | |
Sep 29, 2021 | Assent Application Received |
Oct 05, 2021 | Administrative Review for Completeness |
Oct 05, 2021 | CHA Worksheet received |
Oct 06, 2021 | Bio Team Review for Completeness |
Oct 06, 2021 | Application Accepted |
Oct 07, 2021 | Project Manager |
Nov 05, 2021 | HPHC Historical Preservation No Effect |
Nov 05, 2021 | HPHC Review Pending |
Nov 08, 2021 | Biologist Report |
Nov 10, 2021 | Typist for Processing |
Nov 10, 2021 | Sent to Photo Copy |
Nov 10, 2021 | Executive Sign Off |
Nov 10, 2021 | Permit Approved |
Nov 16, 2021 | Permit Mailed |
Nov 23, 2021 | Land Evidence Date |
Jun 28, 2023 | Modification Request |
Jul 05, 2023 | Administrative Review for Completeness |
Jul 11, 2023 | Bio Team Review for Completeness |
Jul 11, 2023 | Project Manager |
Jul 11, 2023 | Application Accepted |
Jul 19, 2023 | Biologist Report |
Jul 25, 2023 | Modification Approved |
Jul 31, 2023 | Land Evidence Date |
Aug 01, 2023 | HPHC Historical Preservation No Effect |