Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 01, 2021 | Assent Application Received |
Oct 05, 2021 | Administrative Review for Completeness |
Oct 06, 2021 | Bio Team Review for Completeness |
Oct 06, 2021 | Application Accepted |
Oct 06, 2021 | Project Manager |
Oct 07, 2021 | Category A* (Docks) |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Nov 23, 2021 | 30 day Public Notice Issued |
Nov 30, 2021 | US Army Corps of Engineers Approval Received |
Dec 06, 2021 | Plans Received |
Dec 23, 2021 | Public Notice End Date |
Jan 13, 2022 | Public Notice End Date Extension Granted |
Jan 13, 2022 | Objections/Comments Received |
Feb 11, 2022 | Dock Meeting -- Approval |
Apr 12, 2022 | Additional Information Received |
Apr 14, 2022 | Objection withdrawal received |
Apr 21, 2022 | Biologist Report |
Apr 22, 2022 | Typist for Processing |
Apr 22, 2022 | Permit Approved |
Apr 25, 2022 | Permit Mailed |
Apr 29, 2022 | Land Evidence Date |