Action Date | Action Description |
---|---|
Oct 01, 2021 | Assent Application Received |
Oct 06, 2021 | Administrative Review for Completeness |
Oct 13, 2021 | Bio Team Review for Completeness |
Oct 13, 2021 | Application Accepted |
Oct 18, 2021 | Project Manager |
Nov 02, 2021 | HPHC Review Pending |
Nov 02, 2021 | HPHC Historical Preservation No Effect |
Nov 18, 2021 | Additional Information Requested from Applicant |
Nov 24, 2021 | Additional Information Received |
Nov 24, 2021 | Correspondence Received |
Dec 06, 2021 | Correspondence Mailed/Faxed/E-mailed |
Dec 06, 2021 | Additional Information Received |
Dec 17, 2021 | Biologist Report |
Dec 20, 2021 | Permit Approved |
Dec 20, 2021 | Typist for Processing |
Dec 20, 2021 | Executive Sign Off |
Dec 20, 2021 | Sent to Photo Copy |
Dec 21, 2021 | Permit Mailed |
Dec 28, 2021 | Land Evidence Date |