Action Date | Action Description |
---|---|
Oct 08, 2021 | Assent Application Received |
Oct 15, 2021 | Administrative Review for Completeness |
Oct 19, 2021 | Eng Team Review for Completeness |
Oct 19, 2021 | Application Accepted |
Oct 19, 2021 | Category B assigned |
Oct 20, 2021 | Project Manager |
Oct 26, 2021 | HPHC Review Pending |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Nov 15, 2021 | 30 day Public Notice Issued |
Nov 24, 2021 | Additional Information Received |
Nov 24, 2021 | Water Quality Certification |
Dec 15, 2021 | Public Notice End Date |
Dec 28, 2021 | Engineering Report |
Jan 14, 2022 | Ready to Schedule Semi-Monthly Meeting |
Jan 14, 2022 | Mail Agenda Notice |
Jan 25, 2022 | Council Approval Granted |
Jan 25, 2022 | Semi-Monthly Meeting Date Scheduled |
Feb 01, 2022 | Stipulation Package by Engineer |
Feb 01, 2022 | Typist for Processing |
Feb 02, 2022 | Permit Mailed |
Feb 07, 2022 | Land Evidence Date |
Feb 22, 2022 | US Army Corps of Engineers Approval Received |
Mar 23, 2022 | 30 Day Appeal Notification to Owner |
Mar 23, 2022 | Legal Response/Decision |
May 10, 2022 | US Army Corps of Engineers Approval Received |
May 09, 2023 | Modification Request |
May 15, 2023 | Administrative Review for Completeness |
May 16, 2023 | Eng Team Review for Completeness |
May 17, 2023 | HPHC Review Pending |
Jun 08, 2023 | Engineering Report |
Jun 09, 2023 | Typist for Processing |
Jun 09, 2023 | Executive Sign Off |
Jun 09, 2023 | Sent to Photo Copy |
Jun 09, 2023 | Modification Approved |
Jun 19, 2023 | Land Evidence Date |
Jul 18, 2023 | Correspondence Received |