Action Date | Action Description |
---|---|
Oct 13, 2021 | Assent Application Received |
Oct 18, 2021 | Administrative Review for Completeness |
Oct 20, 2021 | Bio Team Review for Completeness |
Oct 20, 2021 | Application Accepted |
Oct 21, 2021 | Project Manager |
Nov 01, 2021 | Additional Information Requested from Applicant |
Nov 23, 2021 | Additional Information Received |
Nov 23, 2021 | Biologist Report |
Jan 14, 2022 | HPHC Review Pending |
Jan 14, 2022 | HPHC Historical Preservation No Effect |
Jan 25, 2022 | Executive Sign Off |
Jan 25, 2022 | Sent to Photo Copy |
Jan 25, 2022 | Permit Approved |
Jan 25, 2022 | Typist for Processing |
Feb 03, 2022 | Permit Mailed |