Action Date | Action Description |
---|---|
Legal Response/Decision | |
Dock Post-Construction Certification by Engineer received. | |
Oct 15, 2021 | Assent Application Received |
Oct 19, 2021 | Administrative Review for Completeness |
Oct 20, 2021 | Bio Team Review for Completeness |
Oct 20, 2021 | Application Accepted |
Oct 21, 2021 | Project Manager |
Oct 21, 2021 | Category A* (Docks) |
Oct 26, 2021 | HPHC Review Pending |
Oct 26, 2021 | HPHC Historical Preservation No Effect |
Nov 23, 2021 | 30 day Public Notice Issued |
Dec 23, 2021 | Public Notice End Date |
Mar 01, 2022 | Plans Received |
Mar 02, 2022 | Biologist Report |
Mar 02, 2022 | Supervisor Biologist SignOff |
Mar 02, 2022 | Supervisor Engineer SignOff |
Mar 03, 2022 | Executive Signoff of Staff Reports |
Mar 03, 2022 | Additional Information Received |
Mar 07, 2022 | Mail Agenda Notice |
Mar 22, 2022 | Council Approval Granted |
Mar 22, 2022 | Semi-Monthly Meeting Date Scheduled |
Mar 23, 2022 | Stipulation Package from Biologist |
Mar 28, 2022 | Typist for Processing |
Mar 28, 2022 | Executive Sign Off |
Mar 28, 2022 | Sent to Photo Copy |
Mar 28, 2022 | Permit Approved |
Mar 29, 2022 | Permit Mailed |
May 02, 2022 | Assent Requirement |
Aug 08, 2022 | Land Evidence Date |