Action Date | Action Description |
---|---|
Oct 18, 2021 | Assent Application Received |
Oct 19, 2021 | Administrative Review for Completeness |
Oct 26, 2021 | Eng Team Review for Completeness |
Oct 26, 2021 | Application Accepted |
Nov 04, 2021 | Engineering Report |
Nov 04, 2021 | Typist for Processing |
Nov 04, 2021 | Permit Approved |
Nov 05, 2021 | Permit Mailed |
Nov 15, 2021 | Land Evidence Date |
Nov 23, 2021 | HPHC Review Pending |
Nov 23, 2021 | HPHC Historical Preservation No Effect |