Action Date | Action Description |
---|---|
Oct 21, 2021 | Assent Application Received |
Feb 07, 2022 | Administrative Review for Completeness |
Feb 07, 2022 | Deficient Application - Owner Notification Sent |
Feb 16, 2022 | Deficient Application Picked Up |
Mar 11, 2022 | Deficiency Response Received |
Mar 21, 2022 | Bio Team Review for Completeness |
Mar 21, 2022 | Deficient Application - Owner Notification Sent |
Jun 06, 2022 | Deficiency Response Received |
Jun 10, 2022 | Bio Team Review for Completeness |
Jun 10, 2022 | Application Accepted |
Jun 13, 2022 | Project Manager |
Jul 07, 2022 | HPHC Review Pending |
Jul 07, 2022 | HPHC Historical Preservation No Effect |
Jul 11, 2022 | Additional Information Requested from Applicant |
Jul 18, 2022 | Correspondence Received |
Jul 22, 2022 | Correspondence Mailed/Faxed/E-mailed |
Sep 23, 2022 | Phone Call |
Oct 05, 2022 | Additional Information Received |
Oct 17, 2022 | Additional Information Received |
Oct 20, 2022 | Additional Information Received |
Oct 21, 2022 | Correspondence Received |
Oct 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
Oct 24, 2022 | Correspondence Received |
Oct 31, 2022 | Correspondence Received |
Nov 21, 2022 | Additional Information Requested from Applicant |
Nov 29, 2022 | Phone Call |
Nov 29, 2022 | Biologist Report |
Nov 30, 2022 | Typist for Processing |
Nov 30, 2022 | Executive Sign Off |
Nov 30, 2022 | Sent to Photo Copy |
Nov 30, 2022 | Permit Approved |
Dec 01, 2022 | Permit Mailed |
Dec 05, 2022 | Land Evidence Date |
Mar 08, 2023 | Commencement of Work Notice received |