Action Date | Action Description |
---|---|
Nov 01, 2021 | Assent Application Received |
Nov 03, 2021 | Administrative Review for Completeness |
Nov 05, 2021 | Bio Team Review for Completeness |
Nov 05, 2021 | Application Accepted |
Nov 05, 2021 | Project Manager |
Nov 23, 2021 | HPHC Review Pending |
Nov 23, 2021 | HPHC Historical Preservation No Effect |
Nov 29, 2021 | Additional Information Requested from Applicant |
Nov 30, 2021 | Additional Information Received |
Dec 06, 2021 | Correspondence Mailed/Faxed/E-mailed |
Dec 22, 2021 | Plans Received |
Jan 05, 2022 | Biologist Report |
Jan 06, 2022 | Permit Approved |
Jan 06, 2022 | Typist for Processing |
Jan 06, 2022 | Executive Sign Off |
Jan 06, 2022 | Sent to Photo Copy |
Jan 07, 2022 | Permit Mailed |
Jan 12, 2022 | Land Evidence Date |