Action Date | Action Description |
---|---|
Nov 17, 2021 | Assent Application Received |
Nov 18, 2021 | Administrative Review for Completeness |
Jan 06, 2022 | Bio Team Review for Completeness |
Jan 06, 2022 | Application Accepted |
Jan 06, 2022 | Project Manager |
Jan 27, 2022 | HPHC Historical Preservation No Effect |
Jan 27, 2022 | HPHC Review Pending |
Mar 21, 2022 | Typist for Processing |
Mar 21, 2022 | Executive Sign Off |
Mar 21, 2022 | Sent to Photo Copy |
Mar 21, 2022 | Permit Mailed |
Mar 21, 2022 | Permit Approved |
Mar 21, 2022 | Biologist Report |