Action Date | Action Description |
---|---|
Nov 22, 2021 | Assent Application Received |
Nov 24, 2021 | Administrative Review for Completeness |
Nov 24, 2021 | CHA Worksheet received |
Dec 13, 2021 | Bio Team Review for Completeness |
Dec 13, 2021 | Application Accepted |
Dec 15, 2021 | Project Manager |
Jan 13, 2022 | HPHC Historical Preservation Comments/Concerns |
Jan 13, 2022 | HPHC Review Pending |
Feb 15, 2022 | HPHC Historical Preservation No Effect |
Feb 18, 2022 | Biologist Report |
Feb 24, 2022 | Typist for Processing |
Feb 24, 2022 | Executive Sign Off |
Feb 24, 2022 | Sent to Photo Copy |
Feb 24, 2022 | Permit Approved |
Feb 28, 2022 | Permit Mailed |
Mar 03, 2022 | Land Evidence Date |