Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 01, 2021 | Assent Application Received |
Dec 02, 2021 | Administrative Review for Completeness |
Dec 07, 2021 | Bio Team Review for Completeness |
Dec 09, 2021 | Application Accepted |
Dec 09, 2021 | Project Manager |
Dec 09, 2021 | Category A* (Docks) |
Dec 15, 2021 | HPHC Review Pending |
Dec 15, 2021 | HPHC Historical Preservation No Effect |
Feb 21, 2022 | Additional Information Received |
Mar 01, 2022 | 30 day Public Notice Issued |
Apr 01, 2022 | Public Notice End Date |
May 06, 2022 | Dock Meeting Scheduled (Admin) |
Feb 24, 2023 | Plans Received |
Apr 06, 2023 | Dock/1.1.6 Review approval |
May 01, 2023 | Engineering Report |
May 16, 2023 | Typist for Processing |
May 16, 2023 | Executive Sign Off |
May 16, 2023 | Sent to Photo Copy |
May 16, 2023 | Permit Approved |
May 18, 2023 | Permit Mailed |
Jun 05, 2023 | Land Evidence Date |