Action Date | Action Description |
---|---|
Dec 02, 2021 | CHA Worksheet received |
Dec 02, 2021 | Assent Application Received |
Dec 02, 2021 | Administrative Review for Completeness |
Dec 07, 2021 | Bio Team Review for Completeness |
Dec 08, 2021 | Eng Team Review for Completeness |
Dec 08, 2021 | Application Accepted |
Dec 08, 2021 | Project Manager |
Jan 05, 2022 | HPHC Historical Preservation No Effect |
Jan 05, 2022 | HPHC Review Pending |
Jan 27, 2022 | Engineering Report |
Jan 28, 2022 | Typist for Processing |
Jan 28, 2022 | Executive Sign Off |
Jan 28, 2022 | Sent to Photo Copy |
Jan 28, 2022 | Permit Approved |
Feb 03, 2022 | Permit Mailed |
Feb 08, 2022 | Land Evidence Date |
Jan 23, 2023 | Modification Request |
Jan 27, 2023 | Administrative Review for Completeness |
Mar 01, 2023 | Bio Team Review for Completeness |
Mar 02, 2023 | Deficient Application - Owner Notification Sent |
Mar 17, 2023 | Deficiency Response Received |
Mar 20, 2023 | Bio Team Review for Completeness |
Mar 20, 2023 | Application Accepted |
Mar 20, 2023 | Project Manager |
Mar 27, 2023 | HPHC Historical Preservation No Effect |
Apr 04, 2023 | Biologist Report |
Apr 11, 2023 | Typist for Processing |
Apr 11, 2023 | Executive Sign Off |
Apr 11, 2023 | Sent to Photo Copy |
Apr 11, 2023 | Modification Approved |
Apr 13, 2023 | Permit Mailed |
Apr 21, 2023 | Commencement of Work Notice received |
May 12, 2023 | Land Evidence Date |