Action Date | Action Description |
---|---|
Dec 14, 2021 | Assent Application Received |
Dec 17, 2021 | Administrative Review for Completeness |
Dec 17, 2021 | CHA Worksheet received |
Dec 22, 2021 | Additional Information Requested from Applicant |
Dec 23, 2021 | Additional Information Received |
Dec 23, 2021 | Application Accepted |
Dec 23, 2021 | Project Manager |
Dec 23, 2021 | Bio Team Review for Completeness |
Jan 14, 2022 | HPHC Review Pending |
Jan 14, 2022 | HPHC Historical Preservation No Effect |
Jan 24, 2022 | Additional Information Received |
Feb 23, 2022 | Biologist Report |
Mar 01, 2022 | Typist for Processing |
Mar 01, 2022 | Executive Sign Off |
Mar 01, 2022 | Sent to Photo Copy |
Mar 01, 2022 | Permit Approved |
Mar 02, 2022 | Permit Mailed |
Aug 08, 2022 | Land Evidence Date |
Apr 13, 2023 | Dock Plate re-issue |