Action Date | Action Description |
---|---|
Dec 15, 2021 | Assent Application Received |
Dec 17, 2021 | Administrative Review for Completeness |
Dec 17, 2021 | CHA Worksheet received |
Dec 21, 2021 | Bio Team Review for Completeness |
Dec 21, 2021 | Application Accepted |
Dec 23, 2021 | Project Manager |
Dec 29, 2021 | Plans Received |
Jan 14, 2022 | HPHC Historical Preservation No Effect |
Jan 14, 2022 | HPHC Review Pending |
Mar 01, 2022 | Biologist Report |
Mar 03, 2022 | Typist for Processing |
Mar 03, 2022 | Executive Sign Off |
Mar 03, 2022 | Sent to Photo Copy |
Mar 03, 2022 | Permit Approved |
Mar 07, 2022 | Permit Mailed |
Mar 14, 2022 | Land Evidence Date |