Action Date | Action Description |
---|---|
Dec 17, 2021 | CHA Worksheet received |
Dec 17, 2021 | Assent Application Received |
Dec 17, 2021 | Administrative Review for Completeness |
Dec 22, 2021 | Bio Team Review for Completeness |
Dec 22, 2021 | Application Accepted |
Dec 23, 2021 | Project Manager |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 25, 2022 | HPHC Review Pending |
Mar 03, 2022 | Biologist Report |
Mar 04, 2022 | Typist for Processing |
Mar 04, 2022 | Executive Sign Off |
Mar 04, 2022 | Sent to Photo Copy |
Mar 04, 2022 | Permit Approved |
Mar 07, 2022 | Permit Mailed |
Mar 11, 2022 | Permit Mailed |
Oct 25, 2022 | Land Evidence Date |
Jun 08, 2023 | Modification Request |
Jun 09, 2023 | Application Accepted |
Jun 12, 2023 | Administrative Review for Completeness |
Jun 16, 2023 | Bio Team Review for Completeness |
Jun 16, 2023 | Project Manager |
Jul 26, 2023 | HPHC Historical Preservation No Effect |
Aug 25, 2023 | Additional Information Requested from Applicant |
Aug 30, 2023 | Biologist Report |
Aug 31, 2023 | Modification Approved |
Aug 31, 2023 | Typist for Processing |
Aug 31, 2023 | Executive Sign Off |
Aug 31, 2023 | Sent to Photo Copy |
Sep 06, 2023 | Permit Mailed |
Sep 18, 2023 | Land Evidence Date |