Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 20, 2021 | Assent Application Received |
Dec 22, 2021 | Administrative Review for Completeness |
Dec 23, 2021 | Category A* (Docks) |
Jan 11, 2022 | Eng Team Review for Completeness |
Jan 11, 2022 | Deficient Application - Owner Notification Sent |
Jan 11, 2022 | Bio Team Review for Completeness |
Jan 20, 2022 | Deficiency Response Received |
Feb 16, 2022 | Eng Team Review for Completeness |
Feb 16, 2022 | Application Accepted |
Feb 16, 2022 | Project Manager |
Feb 21, 2022 | 30 day Public Notice Issued |
Mar 21, 2022 | Public Notice End Date |
May 09, 2022 | Dock/1.1.6 Review approval |
May 12, 2022 | Engineering Report |
May 27, 2022 | Correspondence Mailed/Faxed/E-mailed |
Aug 04, 2022 | US Army Corps of Engineers Approval Received |
Aug 15, 2022 | Typist for Processing |
Aug 15, 2022 | Executive Sign Off |
Aug 15, 2022 | Sent to Photo Copy |
Aug 15, 2022 | Permit Approved |
Aug 15, 2022 | Permit Mailed |
Jan 09, 2023 | Land Evidence Date |