Action Date | Action Description |
---|---|
Dec 28, 2021 | Assent Application Received |
Dec 30, 2021 | Administrative Review for Completeness |
Dec 31, 2021 | Bio Team Review for Completeness |
Jan 10, 2022 | Application Accepted |
Jan 10, 2022 | Project Manager |
Jan 10, 2022 | Eng Team Review for Completeness |
Jan 10, 2022 | Category A* (Docks) |
Feb 22, 2022 | 30 day Public Notice Issued |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 25, 2022 | HPHC Review Pending |
Mar 03, 2022 | Plans Received |
Mar 22, 2022 | Public Notice End Date |
May 06, 2022 | Dock Meeting Scheduled (Admin) |
Jun 02, 2022 | Plans Received |
Jun 09, 2022 | Dock/1.1.6 Review approval |
Jul 13, 2022 | Engineering Report |
Jul 21, 2022 | Typist for Processing |
Jul 21, 2022 | Permit Approved |
Jul 21, 2022 | Permit Mailed |
Jul 28, 2022 | US Army Corps of Engineers Approval Received |
Aug 22, 2022 | Land Evidence Date |
Jun 08, 2023 | Modification Request |
Jun 13, 2023 | Administrative Review for Completeness |
Jun 20, 2023 | Bio Team Review for Completeness |
Jul 05, 2023 | Eng Team Review for Completeness |
Jul 05, 2023 | Deficient Application - Owner Notification Sent |