Action Date | Action Description |
---|---|
Jan 24, 2022 | Assent Application Received |
Jan 27, 2022 | Administrative Review for Completeness |
Feb 10, 2022 | Bio Team Review for Completeness |
Feb 14, 2022 | Eng Team Review for Completeness |
Feb 14, 2022 | Application Accepted |
Feb 14, 2022 | Project Manager |
Mar 04, 2022 | HPHC Review Pending |
Mar 04, 2022 | HPHC Historical Preservation No Effect |
Mar 17, 2022 | Additional Information Requested from Applicant |
Apr 19, 2022 | Additional Information Received |
Apr 19, 2022 | Plans Received |
May 19, 2022 | Additional Information Received |
May 19, 2022 | Engineering Report |
May 24, 2022 | Typist for Processing |
May 24, 2022 | Executive Sign Off |
May 24, 2022 | Sent to Photo Copy |
May 24, 2022 | Permit Approved |
May 24, 2022 | Permit Mailed |
Jun 14, 2022 | Land Evidence Date |