Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 02, 2022 | Assent Application Received |
Feb 03, 2022 | Administrative Review for Completeness |
Feb 11, 2022 | Application Accepted |
Feb 11, 2022 | Project Manager |
Feb 16, 2022 | Eng Team Review for Completeness |
Feb 21, 2022 | 30 day Public Notice Issued |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 25, 2022 | HPHC Review Pending |
Mar 21, 2022 | Public Notice End Date |
May 06, 2022 | Dock/1.1.6 Review approval |
May 27, 2022 | Additional Information Requested from Applicant |
Jun 08, 2022 | Phone Call |
Nov 03, 2022 | Typist for Processing |
Nov 03, 2022 | Executive Sign Off |
Nov 03, 2022 | Sent to Photo Copy |
Nov 03, 2022 | Permit Approved |
Nov 03, 2022 | Engineering Report |
Nov 03, 2022 | Permit Mailed |
Jan 31, 2023 | Land Evidence Date |