Action Date | Action Description |
---|---|
US Army Corps of Engineers Approval Received | |
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Mar 09, 2022 | Assent Application Received |
Mar 21, 2022 | Administrative Review for Completeness |
Mar 24, 2022 | Bio Team Review for Completeness |
Mar 24, 2022 | Application Accepted |
Mar 24, 2022 | Project Manager |
Mar 24, 2022 | Category A* (Docks) |
Apr 01, 2022 | HPHC Historical Preservation No Effect |
Apr 01, 2022 | HPHC Review Pending |
Apr 25, 2022 | 30 day Public Notice Issued |
May 25, 2022 | Public Notice End Date |
Jan 25, 2023 | Biologist Report |
Feb 06, 2023 | Typist for Processing |
Feb 06, 2023 | Executive Sign Off |
Feb 06, 2023 | Sent to Photo Copy |
Feb 06, 2023 | Permit Approved |
Feb 13, 2023 | Permit Mailed |