Action Date | Action Description |
---|---|
Apr 13, 2022 | Aquaculture Application Received |
Apr 25, 2022 | Aquaculture Administrative Review |
Apr 25, 2022 | Water Quality Certification |
Apr 25, 2022 | Category B assigned |
Apr 25, 2022 | Application Accepted |
May 16, 2022 | Project Manager |
May 16, 2022 | 30 day Public Notice Issued |
Jun 16, 2022 | Public Notice End Date |
Jun 30, 2022 | Public Notice End Date Extension Granted |
Oct 03, 2022 | US Army Corps of Engineers Approval Received |
May 15, 2023 | Aquaculture Report |
May 15, 2023 | Mail Agenda Notice |
May 23, 2023 | Council Approval Granted -- Aquaculture |
May 23, 2023 | Semi-Monthly Meeting Date Scheduled |
Dec 12, 2023 | Stipulation Package from Aquaculture Coordinator |
Dec 12, 2023 | Typist for Processing |
Dec 12, 2023 | Permit Approved |
Dec 13, 2023 | Permit Mailed |
Dec 13, 2023 | Executive Sign Off |
Feb 06, 2024 | Aquaculture Lease Payment |
Feb 08, 2024 | Aquaculture Lease Received |