Action Date | Action Description |
---|---|
Jun 08, 2022 | Assent Application Received |
Jun 13, 2022 | Administrative Review for Completeness |
Jun 27, 2022 | Bio Team Review for Completeness |
Jun 27, 2022 | Deficient Application - Owner Notification Sent |
Oct 19, 2022 | Deficiency Response Received |
Oct 26, 2022 | Bio Team Review for Completeness |
Oct 26, 2022 | Application Accepted |
Oct 26, 2022 | Project Manager |
Nov 02, 2022 | Additional Information Received |
Jan 03, 2023 | HPHC Historical Preservation No Effect |
Jan 09, 2023 | Biologist Report |
Jan 11, 2023 | Typist for Processing |
Jan 11, 2023 | Executive Sign Off |
Jan 11, 2023 | Sent to Photo Copy |
Jan 11, 2023 | Permit Approved |
Jan 12, 2023 | Permit Mailed |
Feb 08, 2023 | Land Evidence Date |
Jun 21, 2023 | Commencement of Work Notice received |